On the afternoon of August 5, Vice Chairman of the Khanh Hoa Provincial People's Committee Le Huyen chaired a meeting with departments, agencies, and local authorities to review compensation and site clearance progress for the North-South high-speed railway project section passing through the province.
![]() |
| Le Huyen speaks at the meeting |
According to a report by the Provincial Department of Construction, for component project 1 (the section from Dai Lanh Commune to Nam Ninh Hoa Commune, about 66.16 kilometers long, invested by the Provincial Development Project Management Board), to date, site clearance for resettlement areas has reached the last step according to the process. Nearly 4.4 hectares of land, accounting for 97.31 percent, have been handed over to construction units.
For component project 2 (covering 64.13 kilometers from Bac Nha Trang Ward to Nam Cam Ranh Commune, invested by the Provincial Management Board for Agricultural and Traffic Works Construction Investment Project), to date, site clearance for 7 resettlement areas has reached step nine of the 12-step process.
![]() |
| Leader of the Provincial Management Board for Agricultural and Traffic Works Construction Investment Project reports on the progress of component project 2. |
For component project 3 (covering 61.47 kilometers from Cong Hai Commune to Phuoc Ha commune, invested by the Provincial Construction Investment Project Management Board), to date, site clearance for 9 resettlement areas 61.47 kilometers. Agencies and units are implementing the remaining procedural steps to complete site clearance work.
![]() |
| Local authority speaks at the meeting |
Concluding the meeting, Vice-Chairman of the Provincial People's Committee Le Huyen stressed that the North - South high-speed railway project is a national key project. He requested localities to build plans, roadmaps, and specific completion targets; focus on removing difficulties, and accelerate the site clearance progress of resettlement areas. Departments and sectors must tighten coordination to solve obstacles promptly. The project management boards must proactively select contractors and execute construction upon site handover to ensure implementation progress in 2026.
VAN KY
Translated by H.N