The Central Power Corporation held a ground-breaking ceremony for rural electricity supply from the national power grid...

The Central Power Corporation held a ground-breaking ceremony for rural electricity supply from the national power grid, period 2015-2020, in Cam Duc Town, Cam Lam District on October 15. Present at the event was Nguyen Dac Tai, Vice-Chairman of Khanh Hoa Provincial People’s Committee.

 

k
Ground-breaking ceremony.
 
The project includes 22.446km of medium pressure grids, 174.927km of low pressure grids, 49 transformer stations (5,867kAV) and 7,140 electricity meters, providing electricity for 7,140 households in 190 villages in the 5 districts of Khanh Son, Khanh Vinh, Dien Khanh, Cam Lam and Van Ninh.
 
The investment capital is VND146.322 billion, 85% of which is from the national budget and the rest from the reciprocal capital of the power industry. The project is expected to finish in 2020.
 